Kish Free Zone Organization

Access Roads

Exit

Access Roads

1. Project title: Developing Road Infrastructure and Basic Installations of Kish International Airport

2. Location: In Proximity of Kish International Airport

3. The Project:
Constructing access roads¬, airport area’s and parking’s pathways, Internal power posts¬  and related installations, and water storage tanks of Kish International¬ Airport.
4. Annual Capacity:
5.4 passengers annually
5. Total Area:
No
6. Constructed Area:
No
7. Project Construction period:
18 Months
8. Costs:
350 million IRRs
9. Access to infrastructures

NO Required infrastructure Distance to project site
1 Water on the project site
2 Power  on the project site
3 Tele-communication on the project site
4 Main Road on the project site
5 Airport In the Airport Proximity
6 Harbor 6 Kms



10 - Investment methods

A: Partnership *  B: contracting  C: Absolute purchase of land  D:Rent