Developinging Kish Commercial Port
1. Project title: The Second Phase of Kish Commercial Port Development and Constructing a -35,000ton Container Terminal
2. Location: Kish Commercial Port
3. The Project:
• Supplying, transporting and driving metal piles (9900 tons)
• Drilling and installing 3870 M3 piles, gaskets
• Suppling 320 tons cable to be pre-weaved and used
• 400-ton rebar typing
• 7200 M3 concreting for beams on main piles, tie beams and under-rail beams
• constructing concrete blocks for surfacing 18,000 M2
• Draft: 12.5 ms
4. Annual Capacity: Changes seasonally
5. Total Area: 12,000 M2
6. Constructed Area: No
7. Project Completion period: 5/2 year
8. Costs: 817 million IRRs
9. Access to infrastructures
NO | Required infrastructure | Distance to project site |
1 | Water | On Project Site |
2 | Power | On Project Site |
3 | Tele-communication | On Project Site |
4 | Main Road | On Project Site |
5 | Airport | 13 Kms |
6 | Harbor | On Project Site |
10 - Investment methods
A: Partnership * B: contracting * C: Absolute purchase of land D:Rent